Sections
6 entriesSection 8410Limits a claimant’s ability to enforce a lien to situations in which the claimant has given preliminary notice to the extent required…Section 8412Bars a direct contractor from enforcing a lien unless the contractor records the lien claim after completing the direct contract and before…Section 8414Bars a claimant other than a direct contractor from enforcing a lien unless the claim of lien is recorded after the claimant…Section 8416Requires a mechanics-lien claim to be written, signed, verified, contain specified claim and property information and a 10-point bold notice stating the…Section 8422Allows specified erroneous information in a lien claim without invalidating it, but makes demand, credit, offset, or work errors fatal when intended…Section 8424Allows an owner, direct contractor, or subcontractor disputing a recorded lien to release the property by recording a bond from an admitted…