California Codes, Civil Code - CIV, Division 4 — General Provisions, Part 6 — Works of Improvement, Title 2 — Private Works of Improvement, Chapter 3 — Design Professionals Lien, Section 8312
A design professional shall record a claim of lien under this chapter no later than 90 days after the design professional knows or has reason to know that the work of improvement will not be commenced.
Notes
Requires a design professional to record a claim of lien under this chapter no later than 90 days after the design professional knows, or has reason to know, that the work of improvement will not be commenced. The 90-day period runs from that knowledge or reason-to-know point.
Use as reference
Lexinter.net | California Code, Civil Code - CIV § 8312 | https://laws.lexinter.net/codes/california/civil-code/division-4/part-6/title-2/chapter-3/section-8312