Sections
5 entriesSection 9300Requires a claimant, before giving a stop payment notice or asserting a payment-bond claim, to give preliminary notice to the public entity…Section 9302Requires preliminary notice to comply generally with the referenced chapter. Establishes a special rule for a public works contract constructed by the…Section 9303Requires a preliminary notice to comply with the referenced provision and additionally include a general description of the work to be provided…Section 9304Limits a claimant’s stop-payment-notice and payment-bond rights to work provided within 20 days before the claimant gives preliminary notice and to work…Section 9306Establishes grounds for disciplinary action under the Contractors’ State License Law when a licensed subcontractor whose contract on a particular work of…