(a) Except as otherwise provided by statute, before giving a stop payment notice or asserting a claim against a payment bond, a claimant shall give preliminary notice to the following persons:

(1) The public entity.

(2) The direct contractor to which the claimant provides work.

(b) Notwithstanding subdivision (a):

(1) A laborer is not required to give preliminary notice.

(2) A claimant that has a direct contractual relationship with a direct contractor is not required to give preliminary notice.

(c) Compliance with this section is a necessary prerequisite to the validity of a stop payment notice under this title.

(d) Compliance with this section or with Section 9562 is a necessary prerequisite to the validity of a claim against a payment bond under this title.

Notes

Requires a claimant, before giving a stop payment notice or asserting a payment-bond claim, to give preliminary notice to the public entity and relevant direct contractor. Exempts laborers and claimants contracting directly with the direct contractor, and makes compliance a prerequisite to validity of the stop payment notice or bond claim, subject to the referenced alternative.

Use as reference

Lexinter.net | California Code, Civil Code - CIV § 9300 | https://laws.lexinter.net/codes/california/civil-code/division-4/part-6/title-3/chapter-3/section-9300

Disclaimer: Codes available on Lexinter may not reflect the most current laws in your jurisdiction. We make no warranties regarding the accuracy, completeness, or adequacy of the information provided. Always verify the status of any code with your state legislature or official government sources before relying on it for legal purposes.