If a direct contractor is not paid the amount due pursuant to a written contract within 35 days after the date payment is due under the contract, and there is no dispute as to the satisfactory performance of the contractor, the contractor may give the owner a stop work notice. The notice shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1.
Notes
Allows a direct contractor to give an owner a stop work notice when an amount due under a written contract remains unpaid 35 days after its contractual due date and there is no dispute over satisfactory contractor performance. Requires the notice to comply with the referenced chapter.