(a) If an owner withholds a retention from a direct contractor, the owner shall, within 45 days after completion of the work of improvement, pay the retention to the contractor.

(b) If part of a work of improvement ultimately will become the property of a public entity, the owner may condition payment of a retention allocable to that part on acceptance of the part by the public entity.

(c) If there is a good faith dispute between the owner and direct contractor as to a retention payment due, the owner may withhold from final payment an amount not in excess of 150 percent of the disputed amount.

Notes

Requires an owner withholding retention from a direct contractor to pay it within 45 days after completion of the work of improvement. Allows retention tied to a portion becoming public property to await public-entity acceptance and allows withholding up to 150 percent of a good-faith disputed retention amount.

Use as reference

Disclaimer: Codes available on Lexinter may not reflect the most current laws in your jurisdiction. We make no warranties regarding the accuracy, completeness, or adequacy of the information provided. Always verify the status of any code with your state legislature or official government sources before relying on it for legal purposes.